Tag: thermal power plant

Montenegro faces €70 million electricity challenge due to Pljevlja TPP shutdown

Due to the extended shutdown of the Pljevlja Thermal Power Plant (TPP), Elektroprivreda Crne Gore (EPCG) is expected to spend approximately 70 million EUR...

Pljevlja thermal power plant to undergo reconstruction next year

Reconstruction of the Pljevlja Thermal Power Plant (TPP) is set to begin next year and is projected to take seven months to complete, according...

Management of Montenegro’s EPCG proposes retention of €52.4 million profit, no dividends for shareholders

Elektroprivreda Crne Gore (EPCG) management has recommended to the General Assembly of Shareholders that the entire profit of €52.4 million, earned last year, be...

EPCG faces energy shortfall and ambitious projects ahead

As the Pljevlja Thermal Power Plant gears up for renovations next year, Elektroprivreda Crne Gore (EPCG) anticipates a shortfall of approximately 400 gigawatt hours...
Supported by

Montenegro’s energy sector prepares for thermal power plant shutdown

The upcoming year poses a significant challenge for Montenegro's energy sector, particularly with the Thermal Power Plant Pljevlja expected to be offline for several...

Energy company EPCG reports profitable export, hydrological outlook, and plant maintenance challenges

The power utility company Elektroprivreda (EPCG) has achieved significant exports in the first two months of this year, resulting in a profit of over...