MarketsMontenegro’s power market is turning into a regional gateway as Serbia-to-Italy flows...

Montenegro’s power market is turning into a regional gateway as Serbia-to-Italy flows reshape the outlook

Supported byOwner's Engineer banner

Montenegro’s electricity market is entering a new phase in which its value will increasingly be determined not only by domestic generation and consumption, but by its position between the Western Balkans and Italy.

For years, the Montenegro–Italy submarine cable was viewed primarily as an infrastructure asset giving the small Balkan system access to a large EU electricity market. The emerging opportunity is broader: Montenegro can become a commercial gateway for Serbian and other regional independent power producers seeking Italian offtakers, while simultaneously expanding its own renewable generation and integrating more closely with the EU market.

Supported byElevatePR Montenegro

That combination could strengthen transmission revenues, liquidity and investment in Montenegro. It will also expose the country more directly to volatile Italian prices, congestion, renewable oversupply and increasingly complicated CBAM rules.

The transition is already visible in 2026 electricity prices.

Supported byVirtu Energy

Montenegro’s MEPX day-ahead market recorded an average baseload price of €158.45/MWh in September, with hourly prices ranging from about €84.80/MWh around midday to €245.86/MWh in the evening. That widening intraday spread is becoming one of the defining features of the market: cheaper solar-heavy daytime periods increasingly contrast with much more expensive evening hours when renewable output falls and regional demand remains high. 

Separate CGES procurement auctions for transmission-system losses showed further tightening during October. Baseload procurement moved from around €179/MWh for Sept. 28-Oct. 4, to around €183-185/MWh for Oct. 5-11, €214-220/MWh for Oct. 12-18, and approximately €258-259/MWh for Oct. 19-25. These are small-volume procurement auctions rather than a direct proxy for the wholesale market, but the progression illustrates the increasingly expensive short-term energy environment confronting system operators this autumn. 

For Montenegro, this volatility strengthens the case for more domestic renewable generation, flexible hydropower, storage and regional electricity trading rather than simply maximizing annual generation.

Montenegro moves from import-risk market towards more frequent surpluses

The government’s 2026 Energy Balance planned electricity production of 3,798 GWh, around 57.6% above the estimated 2025 level, with a projected annual surplus of approximately 398 GWh.

The increase was expected to come from the return of the Pljevlja thermal plant following environmental reconstruction and a substantial rise in solar production. The plan envisaged solar capacity reaching roughly 215 MW and total available generation capacity of approximately 1,320 MW by the end of 2026. 

The numbers point towards an important structural change.

Montenegro has historically been highly sensitive to hydrology. In wet periods, its hydropower portfolio can produce significant surpluses. During dry periods or major plant outages, the country can rapidly turn towards imports.

Solar and wind reduce that binary dependence but introduce another problem: greater hourly volatility.

The commissioning cycle around projects such as the 54 MW Gvozd wind farm, EPCG solar developments and private solar plants means Montenegro could increasingly have excess electricity during favourable renewable periods while still facing shortages during evening peaks, droughts or periods of weak wind.

The future market is therefore less about whether Montenegro is an annual importer or exporter and more about when it has electricity available and how much that electricity is worth during a particular hour.

That is exactly where the Italian cable becomes strategic.

Serbia could increase the value of Montenegro’s transmission position

Serbia has a substantially larger electricity system and a growing portfolio of wind and solar IPPs. Some projects are committed through existing long-term arrangements, while others will need merchant sales, corporate PPAs or international traders.

For those producers, the route through Montenegro provides access to Italy.

Electricity can move through the Serbian transmission network, cross into Montenegro and then be commercially delivered through the submarine interconnector into Italy.

From Montenegro’s point of view, this is not simply Serbian electricity passing through the country.

Regional flows create value for CGES, deepen Montenegro’s trading market and improve the economic justification for further transmission investment.

CGES reported €50.3 million of congestion revenues in 2025, up by €8.3 million from the previous year. The company recorded €21 million in net profit, and has explicitly identified international-market revenues, including electricity transit and commercial use of the cable to Italy, as an important part of its financial performance. 

That establishes a direct economic link between regional electricity flows and Montenegro’s domestic transmission economics.

Higher use of the Serbia–Montenegro–Italy corridor can therefore generate benefits even when the electricity itself is not produced in Montenegro.

It can support congestion income, infrastructure investment and a more liquid trading environment, while potentially reducing the portion of network costs that ultimately needs to be recovered domestically.

Montenegro’s geographic position starts to behave like an infrastructure asset.

The cable is valuable precisely because capacity is scarce

The Montenegro–Italy interconnector currently provides 600 MW of physical capacity, although not all of that capacity is continuously available through ordinary public auctions.

Scarcity gives cross-border capacity an economic value, but it also limits the volumes Serbian or Montenegrin producers can reliably commit to Italy.

Recent events illustrate that risk.

For delivery on Oct. 3, CGES curtailed 400 MW of Montenegro-to-Italy long-term transmission rights to zero for six daytime hours because of operational security limitations associated with the HVDC Monita system. A further 400 MW was curtailed for eight hours on Oct. 4. 

Those events do not undermine the strategic case for the cable. They demonstrate why transmission availability has a market price.

A Serbian wind farm may have cheap electricity available and an Italian industrial buyer willing to pay a premium, yet the transaction only works if corresponding capacity exists across both Serbia–Montenegro and Montenegro–Italy.

For Montenegro, this means congestion will remain both an opportunity and a constraint.

Greater regional electricity flows can raise transmission revenues. But excessive congestion can restrict trade, discourage long-term PPAs and prevent renewable projects from capturing higher-priced markets.

The investment case increasingly favours network expansion.

2027: more renewables, greater price dispersion

The first part of the outlook is likely to be defined by greater renewable output combined with continued volatility in European fuel markets.

High gas prices during 2026 have lifted European wholesale electricity prices and increased the value of flexible generation. The IEA expects renewable and nuclear generation to expand further in 2027, but energy prices remain exposed to geopolitical developments and LNG supply conditions. 

For Montenegro, 2027 is likely to bring more frequent periods of low daytime prices alongside expensive evening hours.

The emerging September 2026 price profile already points in this direction.

Solar generation depresses midday prices, while the system becomes tighter after sunset. As Montenegro adds more solar, the value of producing another MWh at noon may decline faster than the value of producing or storing electricity for 19:00 or 20:00.

This will change project economics.

Pure solar projects will increasingly need to evaluate their capture price, rather than using annual baseload prices in financial models.

Wind has a different production profile and can therefore complement solar.

Hydropower becomes more valuable when operators can retain water and generate during expensive hours.

Battery storage could become one of Montenegro’s most valuable new asset classes because it can move electricity between those increasingly divergent periods.

Italy is developing similar characteristics. In October 2026, three Italian market zones recorded negative day-ahead prices for the first time, illustrating how growing renewable penetration is increasing price volatility even in the higher-priced Italian market. 

The future Montenegro–Italy trade will therefore be increasingly about hourly optimisation rather than a simple assumption that Italian electricity is always more expensive.

2028: market coupling could be the biggest structural change

Montenegro has completed the legislative transposition required to progress towards integration with the EU electricity market.

The Energy Community Secretariat has said that full market coupling with the EU could plausibly be achieved by early 2028, subject to compliance verification and completion of the contractual and technical implementation process. Montenegro has identified Italy as the initial natural market-coupling partner because of the submarine connection. 

This could be more important to the market than another individual power plant.

Today, traders explicitly acquire capacity and separately trade electricity.

Market coupling would allow the trading algorithm to optimise electricity and cross-border capacity together, making power flows more responsive to price differences.

For Montenegro this should increase liquidity and connect its relatively small exchange much more directly to a large European market.

But coupling has a second effect that investors should not ignore.

It should gradually compress price differences.

The easy arbitrage opportunity — buying electricity cheaply in Montenegro and selling it at a large premium in Italy — becomes smaller as the two markets become more efficiently integrated.

This does not eliminate trading value. It changes where the value sits.

Flexibility, storage, forecasting, intraday trading and physical renewable PPAs become more valuable, while pure geographical price arbitrage becomes less reliable.

Market coupling is also important to Montenegro’s CBAM strategy. It is one of the prerequisites associated with the potential future electricity exemption, although coupling by itself should not be treated as guaranteeing that exemption.

2029: Serbian grid reinforcement could accelerate north-to-south flows

The next major structural change could arrive from Serbia.

EMS now plans to complete the third section of the Trans-Balkan Electricity Corridor during 2028, followed by the fourth section connecting the Bajina Bašta area towards Višegrad and Pljevlja in 2029. 

For Montenegro, the Pljevlja connection is strategically important.

It would strengthen the high-voltage route carrying electricity from Serbia and the wider region towards Montenegro’s coastal system and the Italian cable.

This could bring a larger pool of generation into competition for the Montenegro–Italy corridor.

Serbian wind and solar plants, hydro production from the wider Drina system, Bosnian generation and Montenegro’s own growing renewable fleet could increasingly compete for access to the same southward route.

Montenegro would consequently become less of an isolated national power market and more of a regional electricity junction between the continental Balkans and Italy.

That is positive for CGES and market liquidity but creates another investment requirement: transmission capacity inside Montenegro and across the Adriatic needs to keep pace with generation development.

Otherwise, the bottleneck simply moves from one part of the corridor to another.

CBAM could determine which electricity actually reaches Italy

The introduction of CBAM has already disrupted the traditional economics of Western Balkan electricity exports.

During the first quarter of 2026, commercially scheduled exchanges between Energy Community markets and neighbouring EU countries fell 25%, despite Contracting Party day-ahead prices averaging around €30/MWh below neighbouring EU markets. The Energy Community has linked part of that divergence to CBAM and the difficulties renewable producers face in demonstrating the actual emissions of exported electricity. 

This matters particularly to Montenegro.

A Serbian renewable plant cannot turn its electricity into Montenegrin electricity simply by transporting it through Montenegro. Its country of production remains Serbia for CBAM purposes.

Likewise, a Montenegrin renewable producer cannot rely only on a renewable certificate if an EU buyer wants to claim actual plant-level emissions.

The commercial chain increasingly requires a physical PPA, hourly generation and nomination matching, metering evidence, transmission documentation and independent verification.

Montenegro can therefore generate another form of value beyond physical transmission: an organised market and technical infrastructure capable of supporting verifiable cross-border green-electricity transactions.

That could become particularly valuable for Italian industrial consumers seeking renewable power with an auditable origin.

Montenegro’s forecast is increasingly about becoming a platform

The base case for 2027-2029 is therefore not simply that Montenegro will produce more electricity.

It is that the country becomes a more complex electricity platform.

Domestic solar and wind generation should increase.

Hydropower remains the main source of flexibility but retains hydrological risk.

Pljevlja continues to provide firm production while facing progressively stronger decarbonisation pressures.

Battery storage becomes economically more relevant as intraday spreads widen.

Market coupling with Italy could significantly improve liquidity from around 2028 if implementation remains on schedule.

The Serbian 400 kV corridor towards Pljevlja could increase regional flows from 2029.

And the Montenegro–Italy cable remains the infrastructure that connects all of those developments to an EU market.

The biggest strategic mistake would be to see Montenegro merely as a transit country.

Its stronger opportunity is to become the trading, transmission and renewable-integration gateway between the Western Balkans and Italy.

That would allow Montenegro to capture value from its own renewable generation, from Serbian and regional IPPs, from transmission congestion and from the growing need for flexible, traceable and CBAM-compatible electricity.

The crucial investment question is therefore shifting. It is no longer simply how many new megawatts Montenegro can build, but how much regional electricity its grid can absorb, optimise, verify and deliver into Europe when that electricity is worth the most.

By Virtu.Energy

Supported byspot_img

Related posts
Related

Supported byspot_img
Supported byspot_img
Supported byMercosur Montenegro - Investing in the future technologies
Supported byElevate PR Montenegro
Supported bySEE Energy News
Supported byMontenegro Business News