Montenegro will have €147.4mn of the European Union’s €150mn support package available directly for construction of the Mateševo–Andrijevica motorway section, after the financing agreement was amended to allocate €2mn to an EBRD grant-management fee and another €600,000 to technical assistance. The change is small relative to the size of the project, but it exposes a more important issue in the financing structure: the winning €693.97mn design-and-build contract is now almost twice as large as the combined direct EU construction grant and EBRD loan, leaving Montenegro responsible for roughly half of the core construction cost before supervision, VAT and other project expenses are considered.
The adjustment should not be interpreted as Brussels withdrawing support from the project. The total €150mn EU allocation remains unchanged. What changes is its distribution. Of the full package, €147.4mn, or about 98.3%, will finance the investment itself, €600,000 will finance technical assistance and €2mn, equivalent to around 1.3% of the original grant, will be retained by the European Bank for Reconstruction and Development for administering the funds.
The amendment became necessary because the EBRD management charge had not been incorporated into the original calculation when the grant agreement was structured. The result is therefore primarily an accounting and financing adjustment rather than a reduction in the EU’s political or financial commitment to Montenegro’s largest current transport project.
That distinction matters because the €150mn package is the largest EU grant awarded to Montenegro for a single infrastructure project. The EU had initially committed €100mn, with another €50mn subsequently added, giving the Mateševo–Andrijevica section an unusually large non-repayable component compared with previous Montenegrin motorway financing.
The economics nevertheless look different once the grant is placed against the construction contract now actually signed.
Monteput selected the POWERCHINA–STECOL–PCCD consortium to design and build the section after a tender conducted under EBRD procedures. Its accepted contract price is €693,969,668.88 excluding VAT. Competing bids were higher, with Cengiz–Azvirt at €735.01mn and China Communications Construction Company at €724.64mn. The winning proposal was therefore around €30.7mn below the second-lowest financial offer and more than €41mn below the highest qualifying bid.
Against that €693.97mn contract value, the revised €147.4mn EU construction grant covers about 21.2%.
The EBRD sovereign loan of up to €200mn covers another 28.8%.
Together, those two direct financing sources amount to €347.4mn, or almost exactly 50.1% of the design-and-build contract. The remaining gap is approximately €346.6mn, equivalent to 49.9%, before additional costs outside the construction contract are added.
That represents a materially different financing balance from the first section of the Bar–Boljare motorway.
The Smokovac–Mateševo priority section, approximately 41km long, was originally contracted at around €809.6mn, with roughly 85% financed through a loan from China Exim Bank. The structure left Montenegro heavily exposed to external debt and became one of the defining sovereign-credit issues of the previous decade as the motorway was built alongside a sharp increase in public indebtedness.
Mateševo–Andrijevica is being financed much more conservatively from a debt-composition perspective. Only around 29% of the core construction contract is directly covered by the EBRD loan, while more than one fifth is financed through non-repayable EU funding. Montenegro is expected to provide the rest from its own resources. (eu.me)
The phrase “own funds”, however, does not necessarily mean that the remaining €346.6mn will ultimately be financed without borrowing. Montenegro runs a fiscal deficit and regularly accesses capital markets, so domestic-budget contributions to the motorway form part of the broader sovereign financing requirement. The EU grant reduces the amount that would otherwise need to be funded by taxes or debt, but it does not eliminate the project’s effect on the public balance sheet.
The distinction is particularly relevant in 2026, when Montenegro is simultaneously managing large infrastructure commitments and refinancing risk.
Gross public debt stood at €5.13bn, or 59.9% of GDP, at the end of the first quarter of 2026, while central-government debt was approximately €5.11bn, or 59.6% of GDP. Government deposits reduced net central-government debt to roughly 52% of GDP. The Ministry of Finance’s latest medium-term framework expects gross public debt temporarily to rise to around 68% of GDP by the end of 2026, largely because the government is pre-financing obligations falling due in 2027, including a €750mn Eurobond, before declining towards 59.9% by 2029.
That makes concessional and grant financing especially valuable.
Every euro provided through the EU grant is a euro Montenegro does not have to raise through conventional sovereign borrowing. The practical fiscal value of the revised €147.4mn investment grant therefore extends beyond the nominal amount: it reduces future interest expenditure and limits the motorway’s contribution to Montenegro’s refinancing needs.
The EBRD loan has another important feature that deserves more attention. The full €200mn facility is divided into two €100mn tranches. The first tranche was to be committed at signing, while the second remains formally uncommitted and is expected to become available around 2028, subject to satisfactory project progress and compliance with environmental and social requirements.
This means Montenegro does not yet have an unconditional €200mn EBRD cheque available from day one.
Near-term committed external project financing is effectively built around the EU grant and the initial EBRD tranche, while access to the second €100mn depends on implementation. For a project running across difficult mountainous terrain, that conditionality increases the importance of maintaining schedule, procurement discipline, environmental compliance and effective project supervision.
The motorway is technically demanding enough to justify that caution.
The Mateševo–Andrijevica section is approximately 22–23km long depending on the measurement used in project documents. It descends from Mateševo at roughly 1,060 metres above sea level towards Andrijevica at around 780 metres and includes the 3.6km Trešnjevik tunnel, 21 bridges with a combined length of about 4.8km, the Andrijevica interchange and associated motorway operating and maintenance facilities. More than a third of the route length is therefore accounted for by tunnels and bridges rather than conventional open-road construction.
The accepted construction price implies roughly €30mn–€31.5mn per kilometre, depending on whether the route is measured at 23km or 22km.
That is substantially above the approximately €19.7mn per kilometre implied by the original €809.6mn contract for the 41km Smokovac–Mateševo section. The comparison is not exact — terrain, structures, inflation, design scope and contract conditions differ — but it demonstrates the exceptionally high capital intensity of extending Montenegro’s motorway through the northern mountains.
The project’s financial envelope has also moved well above earlier assumptions.
When Montenegro and the EU were structuring the additional grant support in 2025, official communications referred to a project value of around €600mn. The construction contract alone is now almost €694mn excluding VAT, roughly €94mn, or about 15.7%, above that earlier reference figure. Supervision and other implementation costs come on top of this.
Monteput has separately contracted Italy’s IRD Engineering to supervise design and construction for €14.45mn excluding VAT, with services planned over 90 months, including the defects-remediation period. That takes the identified contract envelope above €708mn even before VAT and other ancillary expenditure.
This is where the seemingly modest €2.6mn reduction in money available directly for construction should be placed in perspective.
It represents only around 0.4% of the €693.97mn main works contract. The management fee will therefore have virtually no effect on whether Montenegro can afford the section. The much larger fiscal questions concern construction-price discipline, design changes, geological risk, claims under the FIDIC contract and the extent to which the state must finance costs beyond the EBRD and EU envelopes.
A 10% increase in the construction contract, for example, would represent almost €69.4mn, more than 26 times the amount being reallocated away from direct EU construction funding.
The financing architecture is designed partly to reduce that risk.
The project is being implemented under FIDIC Yellow Book design-and-build conditions, placing substantial responsibility for detailed design and execution with the contractor. Procurement has been conducted under EBRD rules rather than through the model used for the first motorway section, while international supervision, technical assistance and lender monitoring add further layers of control.
The €600,000 technical-assistance allocation should therefore not necessarily be viewed as money lost to construction. On a project approaching €700mn, even relatively small improvements in procurement, environmental management, contract administration or claims prevention can generate savings many times larger than the cost of technical support.
The same argument applies, although less comfortably, to the €2mn EBRD administration fee. Its value ultimately depends on whether EBRD involvement reduces financing and implementation risks sufficiently to justify the charge.
Montenegro’s sovereign-credit position makes that governance component financially significant.
S&P currently rates Montenegro B+ with a positive outlook, while Moody’s rates the sovereign Ba3 with a positive outlook. Both agencies improved their outlooks during 2026, reflecting progress in fiscal management, EU integration and macroeconomic resilience, but Montenegro remains below investment grade.
Infrastructure execution therefore feeds directly into the sovereign-risk story.
A motorway programme delivered within a transparent EBRD/EU framework, while public debt remains manageable, strengthens the argument that Montenegro can use borrowing to expand productive infrastructure without repeating the balance-sheet stress associated with the first Bar–Boljare section. Significant overruns financed from the budget would produce the opposite signal.
The country’s cost of debt has already increased despite improved ratings. The average implied cost of public debt rose from around 2.22% in 2022 to about 3.30% in 2025, while annual interest expenditure increased from approximately €92mn to €161mn. Higher European interest rates and the refinancing of older, cheaper liabilities mean new infrastructure borrowing has a much higher opportunity cost than it did a decade ago. (monte.news)
The €147.4mn grant consequently has a much larger economic value than its simple percentage contribution suggests.
Borrowing the same amount at an average cost of around 3%–4% over a long maturity could generate tens of millions of euros of additional interest expenditure over the life of the financing. Grant funding avoids that burden completely.
There is also a strategic reason for the EU to subsidise the route.
Mateševo–Andrijevica forms part of the Bar–Boljare motorway, intended eventually to connect the Port of Bar with Serbia and Central Europe, and has been incorporated into the extended TEN-T Western Balkans–Eastern Mediterranean corridor. The project therefore has cross-border value extending beyond Montenegro itself.
For the domestic economy, its most immediate impact will be on northern Montenegro.
The existing Smokovac–Mateševo motorway transformed access from Podgorica towards the north but currently ends before the road reaches Andrijevica and the Serbian frontier. Extending the motorway further north should shorten journeys, improve road safety and reduce logistics uncertainty for businesses operating between central and northern municipalities.
The full network effect will remain incomplete after Mateševo–Andrijevica opens because further sections are still required towards Boljare and the Serbian border. The economic return on the current €694mn contract therefore depends partly on future investment beyond Andrijevica.
This creates the characteristic problem of large transport corridors: individual sections have limited standalone value compared with the completed network.
For the Port of Bar, the strategic upside lies in creating a modern motorway axis towards Serbia’s much larger consumer and industrial market. For northern Montenegro, the investment can reduce geographical isolation and improve access to tourism, agriculture and industrial projects. For Serbia, completion of the wider corridor would provide another high-capacity route to an Adriatic port.
Those benefits are real but long dated, making construction-cost control essential.
At the current contract value, Montenegro’s own direct contribution to the core works is approximately €346.6mn once the full EBRD loan and revised EU construction grant are counted. Spread evenly over a five-year construction period, that would correspond to roughly €69mn a year, although actual disbursements will follow construction progress rather than a straight line.
The amount is manageable for an economy with estimated 2026 GDP of around €8.6bn, but it competes with other capital expenditure and comes during a period of elevated sovereign refinancing.
The strongest feature of the new financing model is therefore not that Montenegro has avoided debt altogether. It has not. Rather, the state has shifted from the first motorway section’s heavily debt-dependent model towards a blended structure combining EU grants, multilateral lending and national financing.
The grant revision does little to change that balance.
Direct EU construction funding falls by only €2.6mn from the originally advertised €150mn, while the full European support envelope remains intact. The more consequential numbers are the €693.97mn construction contract, the conditional €200mn EBRD facility, the roughly €346.6mn residual construction requirement for Montenegro, and the possibility that additional project expenses push the effective CAPEX above the headline works contract.
Mateševo–Andrijevica will therefore be a test not of whether Montenegro can secure international financing — that part is largely resolved — but of whether it can convert an unusually favourable European financing package into a motorway delivered without another cycle of major cost escalation.
The €147.4mn construction grant gives Montenegro a substantial fiscal cushion. The project’s sovereign-credit outcome will be determined by what happens to the remaining €550mn-plus of construction and associated expenditure during the years in which the road is actually designed and built.











