Montenegro annuls construction ban on Carine’s €80 million coastal resort, orders fresh inspection

Supported byOwner's Engineer banner

Montenegro’s Spatial Planning Ministry has overturned an inspection decision prohibiting construction of the first phase of Carine’s €80 million Novi Novi tourism resort, reopening an administrative dispute over a major coastal development near Herceg Novi.

The ministry accepted an appeal filed by the Podgorica-based developer and annulled the original construction prohibition, issued on May 13, after finding that the inspection authority had failed to provide sufficiently precise factual and legal grounds for its decision.

Supported byElevatePR Montenegro

The ruling, dated November 2, returns the case to the urban planning and construction inspection authority for reconsideration.

The Novi Novi project is planned across approximately 72,866 square metres in Kumbor and Đenovići, close to the existing Portonovi luxury resort.

Supported byVirtu Energy

The development includes a proposed five-star hotel, apartments, hospitality facilities and supporting tourism infrastructure.

Carine previously estimated the first phase at approximately €80 million, covering about 20,000 square metres of land.

The original inspection decision questioned whether the project’s revised design complied with planning conditions, including building heights, permitted land uses and the allocation between hotel accommodation and apartments.

Under the planning conditions cited in the proceedings, at least 70% of the relevant development area must be designated for hotel uses, with other permitted tourism facilities accounting for the balance.

The developer disputed the findings, arguing that the revised project documentation complied with the applicable planning framework.

Carine also challenged the inspection authority’s interpretation of building heights and cadastral restrictions.

The ministry found that the original prohibition had not adequately specified the affected plots, the alleged departures from planning conditions or the documentation considered deficient.

As a result, the decision was annulled for procedural shortcomings.

The ruling does not constitute final confirmation that the resort complies with all planning requirements.

The inspection authority must reassess the relevant facts and issue a new, properly reasoned decision. The ministry’s ruling also does not establish whether other restrictions remain in force.

The investor had previously outlined a phased construction schedule extending to 2031, although the latest administrative proceedings create uncertainty over the original timetable.

For Montenegro’s tourism and construction sectors, the case illustrates the regulatory risks surrounding large hospitality developments, where planning compliance and administrative disputes can affect investment execution.

The immediate commercial question is whether the new inspection proceedings will allow the project to proceed under its existing design or require additional modifications.

The €80 million investment remains a proposed development value rather than evidence of completed expenditure or unrestricted construction approval.

Supported byspot_img

Related posts
Related

Supported byspot_img
Supported byspot_img
Supported byMercosur Montenegro - Investing in the future technologies
Supported byElevate PR Montenegro
Supported bySEE Energy News
Supported byMontenegro Business News