Montenegro has launched a tender for the main design of a new athletics stadium in Podgorica, opening the first major procurement stage for a planned sports complex that could later generate a substantially larger construction contract.
The Ministry of Public Works has estimated the design contract at €387,000 excluding VAT, or around €468,270 including VAT.
The planned stadium would occupy more than 35,000 square metres and accommodate approximately 4,518 spectators.
Plans envisage an eight-lane athletics track and facilities for jumping and throwing disciplines, together with an indoor tunnel that athletes could use for training and warm-ups during poor weather.
The latest procurement covers design rather than construction.
No final construction value has yet been confirmed, meaning the eventual capital requirement could be substantially higher than the initial design contract.
The tender nevertheless creates an immediate opportunity for architectural, structural, mechanical, electrical and specialist sports-infrastructure consultants.
Once designs are completed, the project could generate further contracts for civil works, seating systems, track surfaces, lighting, drainage and sports equipment.
Podgorica has expanded rapidly during the past decade and faces growing demand for modern public infrastructure alongside residential and commercial development.
Sports facilities form part of that broader investment requirement.
For the government, the challenge will be ensuring that the project moves efficiently from design into procurement and construction.
Montenegro has struggled with delays on some capital projects because of incomplete documentation, property issues and tendering problems.
Recent reviews of the capital budget have shown that significant funds can remain unused when projects are not sufficiently prepared before allocations are approved.
Commissioning a detailed main design should reduce some of that execution risk.
A completed technical package can provide more reliable construction-cost estimates and reduce the scope for design changes after works begin.
The proposed athletics stadium also has a wider economic dimension.
Modern sports infrastructure can support competitions, training camps and events that generate hotel and service-sector demand, although those benefits depend on programming and utilisation rather than the facility alone.
The government’s immediate commitment remains limited to project preparation.
A clearer assessment of the investment case will only become possible once the final design, construction estimate, funding source and procurement schedule are established.
For Montenegro’s engineering sector, however, the tender adds another public project to a growing pipeline of design and supervision work linked to infrastructure modernisation.